Spencer Creek Is Being Rebuilt From the Channel to the Trail This Fall

Drive south on Spencer Road past the St. Charles City-County Library on a weekday and the right lane may be coned off, with crews down in the creek bed across the street. A mile or so away on Millwood Drive, flaggers are moving two-way traffic through a single lane. On the Spencer Creek Trail, a stretch of greenway is fenced off.

Those cones belong to separate jobs. One is a city stormwater project, one is a Great Rivers Greenway trail replacement, and on Millwood, Spire utility work is clearing the way for a fourth, the Millwood Crossing project. Each has its own sponsor, budget and calendar. Together they rebuild Spencer Creek at every level: the creek channel, the street crossings and the paved path beside it. Knowing which crew is which tells you what reopens when.

Who is working where

Project Who is behind it Where What it affects Expected timing
Colby Drive stormwater work City of St. Peters Spencer Creek along the west side of Spencer Road, across from the library Periodic right-lane closures on southbound Spencer Road, 7:30 a.m. to 4 p.m. Lane closures from Sept. 30; completion anticipated in November 2026
Spencer Creek Trail replacement Great Rivers Greenway with the City of St. Peters Showboat Circle to Sutters Mill Road Greenway closed during construction No reopening date posted
Spire utility work Spire Millwood Drive, south of Mill Side Drive and north of Red Mill Court Daytime lane closure on southbound Millwood Scheduled from Oct. 26 to mid-November
Centennial Greenway Millwood Crossing Project City of St. Peters with Great Rivers Greenway Trail crossing at Millwood Drive, Tanglewood subdivision Street work at the crossing Follows the Spire work; closure dates not yet posted

The trail closure and the stormwater work meet at the same street. Great Rivers Greenway's closed segment ends at Sutters Mill Road, and the city's creek-stabilization work starts at Sutters Mill Road and runs north. That makes Sutters Mill Road the hinge of the whole corridor this fall. South of it, crews are rebuilding the path. North of it, they are rebuilding the creek bank the path runs beside.

The creek channel across from the library

The Spencer Road lane closures are the most visible part of the work and the oldest part of the plan. City meeting minutes from April 2023 list the Colby Drive project as a response to two problems along this stretch of Spencer Creek: yards flooding, and erosion of the channel bed and banks.

The city's bid description covers a long reach of creek, from Sutters Mill Road north to Rockefeller Lane. That includes about 1,650 feet of channel south of Shadow Creek Drive and about 1,800 feet north of it. The work includes grade-control structures, riparian renovation, honeysuckle management and a bypass pipe. When the project went to bid in late 2024, Kuesel Excavating's base bid came in at $5,204,300. That was a bid figure, not a final cost, but it shows that this channel work is the largest job on the creek by a wide margin.

The current lane closures are for one piece of that scope, a large concrete storm structure being built in the creek just downstream, directly across from the library. The city's Sept. 29 notice says the lane closes only while crews are working, so closure times vary. It asks drivers to zipper merge to keep backups short and expects the work to wrap up in November 2026, weather permitting.

The trail segment that is fenced off

The trail closure belongs to a different project. Great Rivers Greenway's Spencer Creek Trail Improvements page says many sections of the trail were built decades ago and now need replacement or major repair, and that others fall short of the agency's greenway design standards. Its Oct. 15 status update reports that work is underway to replace and widen the greenway between Showboat Circle and Sutters Mill Road, and that the segment is closed until the work is done.

That page does not give a reopening date or a detour. Great Rivers Greenway says construction will come in phases and that it will keep greenway neighbors and visitors updated on closures through the subscribe option at the bottom of the project page. Questions can go to [email protected] or (314) 436-7009.

Millwood Drive gets two rounds of work

The Millwood Drive lane closure scheduled to start Oct. 26 is for Spire utility work. The city expects it to last until mid-November. The road is supposed to fully reopen at the end of each workday, with at least one lane open during the day and flaggers handling two-way traffic. The city's Oct. 22 alert adds that more work on Millwood will follow the utility job, in preparation for the Centennial Greenway Millwood Crossing Project.

That second round is where the trail crosses Millwood Drive in the Tanglewood subdivision. The city's Aug. 27 work-session packet describes it as a realignment of the trail across Millwood, with a project cost of $361,656. Great Rivers Greenway is contributing $150,000 and the city is covering $211,656 from its LPSW fund. The city's bid for the job includes a retaining wall, a concrete barrier, and ADA sidewalk and curb-ramp upgrades at the crossing.

The Board of Aldermen approved the partnership unanimously on Aug. 13. Mid Rivers Newsmagazine reported that at the board's July 23 work session, Parks and Recreation Service Manager Dan Emrick described the Millwood and Tanglewood alignment as "in need of a lot of attention." He told the board the city would handle demolition, street work, traffic devices, fencing and landscaping in-house, and would hire an outside contractor for the retaining walls and the rock steps in the creek channel. He projected a road closure of three to six weeks, during work hours only, "likely in the October/November timeframe." He said most of the construction would be done by December, with final landscaping in April 2027.

That timeline was a projection from the summer. The city's October alert now puts Spire's utility work in the late-October-to-mid-November slot on Millwood, with the crossing work to follow it. The city has not yet published closure dates for the crossing itself, so the road closure Emrick described is still to come.

What the finished corridor is meant to connect

The trail work fits a larger plan. Great Rivers Greenway's stated goal is to extend the Centennial Greenway along the Spencer Creek Trail from McClay Road, at Harvester Church-The Nazarene, to St. Peters City Centre. That is about 3.75 miles, ending at Mexico Road. The upgrades include a wider paved trail, new bridges, grade corrections to meet ADA accessibility guidelines, and new signage. The Millwood crossing and the Showboat-to-Sutters Mill replacement are two pieces of that plan.

The north end of the corridor is City Centre, where the trail area takes in City Centre Park, the Rec-Plex and City Hall. The city's packet frames the improvement corridor as running between McClay Road and Mexico Road and Ollie's Fun Forest. Ollie's Fun Forest, at 101 City Centre Park Drive, is the city's ADA-compliant playground, with accessible play structures, wide paths and ramps, and perimeter fencing. A trail built to ADA grades that ends at a playground built to the same standard is a fair summary of what the phased work is meant to deliver.

The City Centre end of the trail this season

The north end of the trail stays busy while the middle is under construction. Here is the city's calendar for the next six weeks around City Centre:

  1. Oct. 29 through Nov. 6. The Rec-Plex indoor leisure pool is closed for repairs.
  2. Wednesday, Nov. 11, 10 a.m. to noon. The city's free Veterans Day Ceremony is held at the Cultural Arts Centre, One St. Peters Centre Blvd.
  3. Friday, Dec. 4, 5:30 to 8:30 p.m. The Tree Lighting Ceremony at St. Peters City Hall, 1 St. Peters Centre Blvd., includes a Holly-Day Market, a Gingerbread House Contest, live entertainment and visits with Santa.
  4. Saturday, Dec. 5, 2 to 4 p.m. The St. Charles County Symphony Orchestra plays its Holiday Concert at the Cultural Arts Centre. Tickets are $10.

If the stormwater structure across from the library finishes in November as the city expects, the Spencer Road lane closures should be over before the tree lighting. Spire's Millwood work is also slated to end by mid-November, which leaves the crossing work and the Showboat-to-Sutters Mill trail segment as the projects still underway into December. The city posts trail updates at stpetersmo.net/trails and street updates at stpetersmo.net/streets, and the free StPetersMO app can send closure notifications.

At Patton Properties, we track public projects like the Spencer Creek work because creek-channel and trail upgrades change how a street lives day to day and how a home near the corridor is valued. If you own near Spencer Road, Millwood Drive or the Tanglewood crossing and want to talk through what the finished greenway could mean for your property, contact us.

Work With Us

At Patton Properties, we combine expertise, innovation, and a client-first approach to deliver exceptional results. Whether you're a homeowner, investor, or business owner, we have the skills and resources to turn your real estate goals into reality. Let’s build something great together. Experience the difference with Patton Properties today!